Swimming pool building time: from planning to installation, how long it will take
Video transcription: A lot of people who come into my display centre to have an early-stage think about getting a pool always want to know what is involved in getting a pool. Among a hundred different things that are important when you’re planning a pool, how long it takes comes up pretty often.
You need to, I think, nut it down into four areas. They are planning the pool, getting the approval to build the pool and having the pool built, so that is effectively the installation of the pool. That is before all the nice cosmetic, easier things like the fencing and the paving all come to fruition.
To plan your pool, you can take as long as your want. At the end of the day, you’ve got to make the decision. Planning your pool involves going and having a look at what pool suits you, working thorough the options and the recommendations, and then saying, yes, this is right for me. I like this pool, this size, this colour, with this operating system. I can see myself using it like this, this and this, ticking all the boxes. I’m happy to be doing business with you. You’re a builder, I like the people who are going to be putting it in, I’m happy to go ahead.
When that happens, a contract is drawn up. A contract is the agreement, as the pool builder I’m going to do x, y and z; as the customer, you’re going to do x, y and z and we’re going to go ahead with it.
Your approval, depending on whether you’re going through a council body or a private certifier, it doesn’t matter too much which, that roughly, depending on councils, is a four to six week process. During that time, I always tell my customers, we’ve got this time when no one can really do anything. This is good opportunity to go and have a bit of a look around at pavers and different finishers and things like that.
Once you get your approvals back, they come to us as the builder and we say, yes, absolutely, they can have a pool, we’re all good to go. Then your pool gets custom-made for you. We like to allow, depending on the time of the year really, three to five weeks in the manufacturing process of the pool. It’s made, it’s ready for you and then you move into a construction schedule.
A construction schedule is one of those things that can move around a fair bit. So you’ll always give a tentative install date but we’re not weather gods. We never know what is going to happen with the weather. You may be jumped forward a week or you might be pushed out for two weeks. But that whole process in its entirety from you making the decision and we’re good to go, is often between a five to ten week process, realistically.
There are things that come up. You could all of a sudden, it has happened to me, people have said, school holidays. We’re going away. You had me booked for this stage, can we be two weeks later? Most pool builders can easily work with that. The time really is on you and when you can make a decision, the weather, what it’s doing and of course your councils. You definitely don’t want to be planning a pool in November thinking Christmas day is going to be at your place. That is not going to happen. Give one of the team a call today on 1300 667 445.